Introduction
Deck posts and footings are structural work, which means they live under the building code — and the code has opinions about your post sizes, spacing, footing depths, and connectors. This guide explains what the code framework (primarily IRC Section R507) covers, when you need a permit, and how inspections work, while deferring every jurisdiction-specific number to your local building department. Use the Deck Post Calculator for planning quantities, then verify the structural decisions against your local amendments before you build.
What IRC Section R507 Covers
The International Residential Code’s deck provisions, Section R507, are the prescriptive backbone most US jurisdictions adopt (sometimes with local amendments). For posts and footings, R507 addresses: maximum beam spans between posts (the span tables that cap post spacing, typically yielding 6-8 ft / 1.83-2.44 m layouts for common residential beams), post size minimums tied to deck height and load, footing size minimums, the requirement that footings bear on undisturbed soil below the frost line, and connector requirements between posts, footings, and beams.
The key concept is “prescriptive”: if your deck fits within R507’s tables and limits, you can build to the tables without hiring an engineer. Step outside them — unusual spans, tall posts, heavy loads like hot tubs, or atypical soils — and the code requires engineered design. Your local amendments may tighten any of these values, so the R507 tables are the starting point of the conversation with your building department, not the final word. The formula guide shows how the span-table spacing limit flows into your post count.
Permits: When You Need One
As a rule of thumb, any deck with structural posts and poured footings needs a building permit. Common triggers include: any deck attached to the house, any freestanding deck above a modest height threshold (often around 30 inches / 76 cm above grade, though this varies), and any deck with a roof or cover. Some jurisdictions exempt small ground-level platforms; many do not — never assume.
The permit application typically wants a site plan showing the deck location and setbacks, a framing plan with post locations, sizes, spacing, beam sizes, and footing diameters and depths, plus details of connectors. Preparing this package is exactly what the estimating guide walks you through. Permit fees are usually modest (often $100-$300 for a residential deck) and the review catches design errors before they are buried in concrete — treat it as cheap engineering review, not red tape.
Frost Depth and Footing Requirements
The universally enforced rule: the bottom of every footing must sit below the locally established frost depth so seasonal freezing cannot heave the deck. Frost depth is intensely local — under a foot in the deep south, 4 feet (1.22 m) or more across the northern tier — and your building department publishes the number for your address. This is the single most common inspection failure for DIY footings, and the common mistakes guide explains why there is no cheap fix after the pour.
Related footing rules inspectors enforce: footings must bear on undisturbed (not backfilled) soil, post bases must provide a positive mechanical connection between post and concrete (not just gravity), and wood must be held off the concrete by standoff bases or equivalent. In high-wind or seismic zones, expect additional uplift and lateral connection requirements — ask your building department what applies locally.
The Inspection Sequence
Plan for three inspections, scheduled in this order:
- Footing inspection — called before any concrete is poured. The inspector checks hole depths (tape measure against the frost line), diameters, soil conditions, and rebar or anchor bolt placement. This is the inspection that fails most often; have your batter-board strings still up to prove layout.
- Framing inspection — called after posts, beams, and joists are up but before decking hides the connections. The inspector checks post sizes, spacing, plumb, beam-to-post connections, and hardware against the approved plan.
- Final inspection — after railings, stairs, and finishes. Guardrail post spacing (6 ft / 1.83 m maximum), rail height, and stair details get checked here.
Never pour concrete or cover framing before the corresponding inspection is signed off — inspectors can and do require uncovering work, at your expense. Keep a copy of the approved plans on site; the inspector compares what was approved to what was built.
What to Ask Your Local Building Department
- What is the frost depth for my address, and is there a minimum footing diameter for 6×6 posts?
- Are there local amendments to IRC R507 I should know about (spans, post sizes, connectors)?
- What drawings do you need for the permit, and what is the typical review time?
- How do I schedule each inspection, and how much notice do you need?
- Are there additional requirements for my zone — high wind, seismic, wildfire interface, or floodplain?
- Is notching of posts permitted here, or must beams be through-bolted / capped?
Bring your post layout and footing schedule to this conversation — quantities from the Deck Post Calculator plus the questions above will get you precise answers in one visit instead of three.
Related Guides
- Deck Post Complete Guide — the flagship overview of posts, spacing, and footings.
- Deck Post Common Mistakes — the violations inspectors see most, and their fixes.
- DIY vs Hiring a Pro — who pulls the permit and meets the inspector under each path.
- Deck Post Material Guide — treatment ratings and connectors inspectors expect to see.
- Deck Post FAQ — quick code-adjacent questions answered.
Get Your Number
Code compliance starts on paper: lay out your posts and footings in the Deck Post Calculator, take the resulting schedule to your building department with the questions above, and adjust to their answers before you dig. The calculator gives you the quantities; your local authority gives you the rules — together they produce a deck that passes inspection the first time.
Disclaimer: Code requirements vary by jurisdiction and change over time; nothing here substitutes for your local building department’s current rules. Results are planning estimates only. Verify quantities with your supplier and consult a licensed professional or your local building authority for structural or code-related decisions.